Hinkley Point C delayed by a year as cost goes up by £3bnon May 20, 2022 at 9:59 am

- Advertisement -
- Advertisement -
- Advertisement -
- Advertisement -

The revised operating date for the Somerset site is June 2027 and is expected to cost up to £26bn.

Hinkley Point C Construction site

Image source, EDF

The nuclear power station being built at Hinkley Point will start operating a year later than planned and will cost an extra £3bn, EDF has said.

The revised operating date for the site in Somerset is now June 2027 and total costs are estimated to be in the range of £25bn to £26bn.

EDF said it would have no cost impact on British consumers or taxpayers.

The French energy giant develping the site largely put the delays down to the impact of the pandemic.

EDF has published the findings of a review into the cost and schedule of the power station, taking into account the continuing impact of the Covid-19 pandemic.

Construction work at Hinkley Point C

Image source, EDF

A reduction in workers allowed on site due to Covid safety measures had resulted in the loss of more than half a million days of critical work in 2020 and 2021, it said.

Stuart Crooks, managing director of Hinkley Point C, said they had to “suddenly cut numbers on site from more than 5,000 to around 1,500”.

He added this meant “we had no choice but to become less efficient” with the supply chain “also hit hard”.

“In April 2020, 180 suppliers were fully shut down, but even as late as February this year, more than 60 suppliers were operating with reduced productivity due to Covid,” he said.

Hinkley worker

Mr Crooks said that in January 2021, EDF estimated a six-month Covid impact, assuming an imminent return to normal conditions, but then a second wave of Covid-19 hit.

“In total, the start date for Unit 1 has gone back 18 months since construction started in 2016.

“In such a complex project, it wouldn’t be credible to say we can measure exactly how much of this is due to Covid-19 impact, but it is clearly in excess of 12 months.”

Mr Crooks said “other factors have affected the schedule and costs” and the firm is “facing the same issues as other major projects with UK-wide supply and labour shortages and inflation”.

A government spokesman confirmed: “While the Covid pandemic has understandably led to delays, the revised Hinkley Point C construction forecast will have no impact on British billpayers or taxpayers, with any increase in costs borne entirely by the developers.”

The spokesman continued: “We will continue to work closely with EDF to bring Hinkley Point C to completion, the first new nuclear power station in a generation, which has created and supported over 22,000 jobs across the UK.

“New nuclear power is essential to the UK’s energy security, providing clean and affordable homegrown power.”

Presentational grey line

Follow BBC West on Facebook, Twitter and Instagram. Send your story ideas to: bristol@bbc.co.uk

Related Internet Links

The BBC is not responsible for the content of external sites.
- Advertisement -

Discover

Sponsor

Latest

Turkey earthquake: Hope as foreign help arrives in quake-ravaged Antakyaon February 8, 2023 at 10:10 pm

After a slow initial response, roads into the city are now gridlocked with aid vehicles arriving.After a slow initial response, roads into the city...

Cost of living: Man takes on four jobs to keep his business afloaton November 2, 2022 at 6:18 am

Lee Murthwaite is seeing a 400% increase in energy bills at the recording studio he owns.Lee Murthwaite is seeing a 400% increase in energy...

Bangkok: Exploring a lost world in an abandoned department storeon February 21, 2022 at 12:06 am

A group of artists and architects have turned a derelict building into an art and light exhibit.

Sasha Johnson: Five held on suspicion of attempted murderon May 26, 2021 at 1:34 pm

Five males, aged between 17 and 28, are arrested on suspicion of attempted murder.Five males, aged between 17 and 28, are arrested on suspicion...

Waste collection changes risk chaos, councils warnon March 20, 2023 at 9:10 am

Councils say government plans for consistent waste policies across England could be unworkable.Image source, Getty ImagesBy Joshua NevettBBC PoliticsThe UK government's plans to introduce...