An infrastructure watchdog gives the project a “red” warning, raising issues over budgets and schedules.

A worker at the HS2 construction site at Euston in LondonImage source, Reuters

The HS2 rail line has been given an “unachievable” rating by an official watchdog.

It has been given a “red” warning for its first two phases – from London to Birmingham then onto Crewe – by the Infrastructure and Projects Authority.

The project aims to create high-speed rail links between London and central and northern England, but has faced major delays and criticism.

The government says it remains committed to delivering HS2.

The red rating came in the IPA’s annual report on major projects, which was published on 20 July and gave a snapshot of progress on 244 projects.

The IPA describes itself as the government’s centre of expertise for infrastructure and major projects, and reports to the Cabinet Office and HM Treasury.

Under the IPA’s grading system, a red rating implies: “Successful delivery of the project appears to be unachievable.”

The rating also means there are “major issues with project definition, schedule, budget, quality and/or benefits delivery, which at this stage do not appear to be manageable or resolvable”.

“The project may need re-scoping and/or its overall viability reassessed.”

The phase of the project running from Crewe to Manchester was given an “amber” grading by the IPA, under which successful delivery of a project “appears feasible”, but “significant issues already exist”.

The London to Birmingham leg of HS2 was due to open in 2026, but is now expected between 2029 and 2033.

The second phase was due to open in 2032-33, but has been pushed back to 2035-2040.

An eastern leg of the line running to Leeds has been scrapped, and instead a shorter high-speed line will link Birmingham and East Midlands Parkway.

Map showing route of HS2 rail line

Management issues and unrealistic land valuations have also caused costs to spiral.

A budget of £55.7bn for the whole project was set in 2015, but the target cost excluding the eastern leg of Phase 2b from the West Midlands to the East Midlands has soared to between £53bn and £61bn at 2019 prices.

Earlier this month, HS2 Ltd’s chief executive Mark Thurston announced his resignation – he will leave his role in September after six and a half years.

His resignation came as phase one of the project between London and Birmingham is under construction, with major work taking place at more than 350 sites.

In March, Transport Secretary Mark Harper announced work at London Euston would be paused for two years after costs increased from £2.6bn to £4.8bn.

A spokesperson for the Department of Transport said: “We remain committed to delivering HS2 in the most cost-effective way for taxpayers.

“HS2 will bring transformational benefits for generations to come, improving connections and helping grow the economy.”

Related Topics

- Advertisement -

Discover

Sponsor

Latest

Ex-Marine charged with New York subway chokehold death of Jordan Neelyon May 12, 2023 at 5:36 pm

Daniel Penny, 24, faces up to 15 years if convicted of the death of 30-year-old Jordan Neely.Image source, Michael M. SantiagoA former US Marine...

Arthur Labinjo-Hughes: Boy cried ‘no-one loves me’ before deathon November 24, 2021 at 3:52 pm

Recordings of Arthur Labinjo-Hughes are released as his father and stepmother deny his murder.Image source, West Midlands Police Audio recordings of a six-year-old boy...

Move Notting Hill Carnival to a park – Tory mayoral candidateon August 30, 2023 at 1:31 pm

The comments by Tory London mayoral candidate Susan Hall follow eight stabbings over the weekend.The comments by Tory London mayoral candidate Susan Hall follow...

Conjoined twins separated with the help of virtual realityon August 1, 2022 at 12:05 pm

Surgeons say space-age technology helped doctors in separate countries to work together.Image source, PA MediaBrazilian twins who were joined at the head have been...

England v New Zealand: Jonny Bairstow takes three early catches at Lord’son June 2, 2022 at 11:10 am

Jonny Bairstow takes three catches as England remove Will Young, Tom Latham and Devon Conway in the first hour on day one of the...